Tanker Inspection and Testing Procedure

Follow these structured procedures to ensure safe and compliant tanker operations

Vessel Inspection Procedures

These procedures outline the critical steps for verifying the structural integrity and condition of tanker vessels. Thorough vessel inspection helps prevent leaks, structural failures, and ensures regulatory compliance.

External Shell Inspection

  • Position tanker on level ground with adequate lighting
  • Systematically examine entire shell for dents or deformation
  • Inspect all welds for cracks, corrosion, or deterioration
  • Check for signs of metal fatigue or stress fractures
  • Examine protective coatings for bubbling or peeling
  • Look for evidence of previous repairs or modifications
  • Check mounting points and supports for security
  • Document any abnormalities with photos and measurements

Internal Vessel Inspection

  • Verify confined space entry permit and safety protocols
  • Test atmosphere for oxygen levels and hazardous vapors
  • Use explosion-proof lighting for thorough examination
  • Inspect internal surfaces for corrosion or erosion
  • Check baffles and bulkheads for structural integrity
  • Examine internal lining or coating if applicable
  • Look for product residue, contamination, or buildup
  • Verify drain system functionality and cleanliness

Weld Seam Examination

  • Clean weld areas to ensure clear visibility
  • Conduct visual inspection of all accessible welds
  • Use dye penetrant testing for surface crack detection
  • Look for pitting, porosity, or undercutting in welds
  • Check for misalignment or improper weld profiles
  • Examine heat-affected zones for signs of weakness
  • Verify documentation of previous weld repairs
  • Document any weld defects with precise location notes

Thickness Testing Procedure

  • Calibrate ultrasonic thickness testing equipment
  • Establish grid pattern for systematic testing
  • Clean test points to ensure good contact
  • Take readings at predetermined locations
  • Pay special attention to high-wear areas
  • Compare readings to minimum thickness requirements
  • Document all measurements with precise locations
  • Flag any areas below threshold for further evaluation

Valve & Piping System Procedures

These procedures focus on the critical components that control product flow and containment. Proper valve and piping inspection prevents leaks, ensures proper operation, and maintains system integrity.

Discharge Valve Testing

  • Visually inspect valve for external damage or corrosion
  • Check valve operation through full range of motion
  • Verify proper seating and sealing when closed
  • Test for smooth operation without binding
  • Examine valve seals and gaskets for deterioration
  • Ensure all mounting hardware is secure
  • Verify valve locks and safety features function properly
  • Test for leakage using appropriate methods

Emergency Valve Verification

  • Locate and identify all emergency shut-off valves
  • Test manual operation of emergency valves
  • Verify remote activation systems function properly
  • Check that valves close completely and rapidly
  • Ensure valve controls are clearly marked and accessible
  • Test interlocks and fail-safe mechanisms
  • Verify emergency valve responds within time standards
  • Document emergency valve test results with timestamps

Piping System Inspection

  • Trace entire piping system from inlet to discharge
  • Check all pipes for external damage or corrosion
  • Inspect all connections, flanges, and fittings
  • Verify appropriate gaskets are installed and intact
  • Test all flexible connections for wear or damage
  • Check pipe supports and mounting brackets
  • Look for signs of leakage at all connection points
  • Verify pipe system matches approved configuration

Pressure Relief System Check

  • Verify pressure relief valves are correctly rated
  • Check that tamper-evident seals are intact
  • Confirm calibration records are current and available
  • Inspect pressure relief valve mounting
  • Ensure discharge paths are unobstructed
  • Verify pressure settings match specification
  • Test manual release mechanisms if equipped
  • Document pressure relief system condition and settings

Pressure Testing Procedures

Pressure testing is critical for validating vessel and system integrity. These procedures ensure that proper testing methods are followed to verify containment capabilities while maintaining safety throughout the testing process.

Hydrostatic Test Preparation

  • Review vessel specifications and test requirements
  • Verify test pressure does not exceed 150% of MAWP
  • Clean vessel interior thoroughly before testing
  • Fill vessel completely with water, eliminating air pockets
  • Install calibrated pressure gauges at appropriate points
  • Ensure all vents are closed and sealed
  • Set up proper barricades and warning signs
  • Brief all personnel on test procedures and safety protocol

Hydrostatic Test Execution

  • Increase pressure gradually in predetermined increments
  • Hold pressure at 25%, 50%, 75% of test pressure for checks
  • Inspect for leaks at each pressure increment
  • Once at full test pressure, maintain for required duration
  • Monitor pressure gauge for any pressure drops
  • Document pressure readings at regular intervals
  • Inspect all testable areas for signs of leakage
  • Release pressure gradually after successful completion

Pneumatic Testing (When Required)

  • Verify pneumatic testing is appropriate for the vessel
  • Limit test pressure to 110% of MAWP
  • Fill vessel with compressed air or inert gas
  • Apply soapy water solution to all connections
  • Increase pressure in small increments
  • Observe for bubble formation indicating leaks
  • Maintain heightened safety precautions due to stored energy
  • Release pressure very slowly after test completion

Leak Detection Methods

  • Apply soap solution to external surfaces for bubble testing
  • Use pressure decay testing for small leaks
  • Apply vacuum box testing for weld seam examination
  • Implement helium leak detection for precision testing
  • Use acoustic emission testing for pressure vessels
  • Apply tracer gas methods for system testing
  • Document all test methods and results systematically
  • Photograph any detected leaks for documentation

Cleaning Verification Procedures

Proper cleaning verification ensures product integrity and prevents contamination. These procedures outline the steps for validating cleanliness standards appropriate to the tanker's intended cargo.

Pre-Cleaning Inspection

  • Review records of previous cargo transported
  • Determine cleaning requirements based on next cargo
  • Identify potential cross-contamination concerns
  • Check for product compatibility issues
  • Document pre-cleaning condition with photos
  • Identify problematic residues requiring special attention
  • Develop cleaning plan based on inspection findings
  • Select appropriate cleaning methods and chemicals

Cleaning Verification Protocol

  • Ensure proper lighting for thorough visual inspection
  • Perform white-glove or wipe test on interior surfaces
  • Check for residual odors that may indicate contamination
  • Inspect all internal fittings and difficult-to-clean areas
  • Verify drain valves and low points are residue-free
  • Check for water or cleaning solution remaining in tank
  • Document all verification steps with date and time
  • Obtain verification signature from qualified inspector

Chemical Testing Methods

  • Select appropriate chemical testing based on previous cargo
  • Perform pH testing to verify neutrality if applicable
  • Conduct specific tests for chemical residues
  • Test for chloride content when required
  • Collect samples from multiple tank locations
  • Document all test results with location information
  • Compare results to established acceptance criteria
  • Maintain chain of custody for all test samples

Food Grade Verification

  • Implement stricter cleanliness standards for food transport
  • Verify absence of allergens from previous cargoes
  • Conduct ATP testing for biological contamination
  • Perform microbiological sampling when required
  • Check for cleaning chemical residues that could contaminate food
  • Issue food-grade cleanliness certification
  • Document cleaning methods and sanitization procedures
  • Maintain records for regulatory compliance

Regulatory Compliance Procedures

These procedures ensure that tanker inspections meet all applicable regulatory requirements and that proper documentation is maintained for compliance verification.

Documentation Verification

  • Check that inspection certification is current
  • Verify pressure test records meet required frequency
  • Confirm thickness test documentation is complete
  • Review repair and maintenance history records
  • Ensure all modifications have proper approvals
  • Verify cleaning certificates are appropriate for cargo
  • Check that specification plates are legible and current
  • Confirm all required documentation is readily available

Hazardous Materials Compliance

  • Verify hazardous materials placards are correct and visible
  • Check for proper UN/NA identification numbers
  • Confirm shipping papers are complete and accurate
  • Verify emergency response information availability
  • Check that pressure relief valves meet hazmat requirements
  • Ensure venting systems comply with product specifications
  • Verify tank test pressure rating meets product requirements
  • Document all hazardous materials compliance checks

DOT/TC Inspection Requirements

  • Verify current specification markings are correct
  • Check test date markings are within required intervals
  • Confirm test pressure markings match specifications
  • Verify inspector approvals for previous tests
  • Check that tank meets requirements for intended cargo
  • Verify owner/operator information is current
  • Ensure registration numbers are properly displayed
  • Document compliance with all applicable regulations

Certification Process

  • Complete all required inspection forms accurately
  • Document any deficiencies with corrective actions required
  • Obtain required signatures from qualified inspectors
  • Issue appropriate certification based on inspection results
  • Apply certification markings to tanker as required
  • Update electronic and physical documentation systems
  • Establish next inspection date based on requirements
  • File copies of all certifications per regulatory standards